Childress
Project of IREN
Capacity
What has actually been delivered, against what has been promised. Each figure links to the statement it came from.
| Stage | Capacity | As of | Source |
|---|---|---|---|
| Energized power flowing today | 50 MW | 2026-09-01 | Horizon 1 delivered (50 MW liquid-cooled GPU facility) |
| Contracted a customer is on the hook | 150 MW IT load | 2026-08-31 | Microsoft Horizon data center deliveries |
| Under construction | 100 MW | 2023-12-14 | 100MW data center expansion at Childress |
| Permitted | -- | ||
| Interconnect approved utility has agreed to deliver | -- | ||
| Interconnect requested in a queue, nothing approved | -- | ||
| Announced a press-release figure | 500 MW | 2023-12-14 | Additional power capacity at Childress |
Who has claimed this site
Capacity commitments in the order they were announced. A commitment that ended shows why.
2025-11-02
Microsoft Corporation - anchor tenant · 150 MW · 5-year term source
Claims about this project
2023-11-29 - stated
100MW Childress data center early works 100.0 MW.
2023-11-29 - delayed
2023-12-14 - delayed
2023-12-14 - stated
Additional power capacity at Childress 500.0 MW.
2023-12-14 - stated
100MW data center expansion at Childress 100.0 MW.
2024-05-14 - delayed
2026-05-25 - stated
2026-05-31 - stated
2026-08-12 - stated
2026-08-13 - stated
2026-08-17 - stated
Horizons 2-4 deployment schedule. Promised by 2026-12-31.
2026-08-17 - stated
2026-08-17 - stated
Horizon 1 GPU deployment capacity 50.0 MW.
2026-08-21 - stated