2026 Capacity Expansion to 480MW
Company: IREN - Project: Childress
The claim, verbatim
Horizon 1-4 data center deployment at Childress on track for delivery by year-end 2026 with 480MW capacity, fully contracted
Source (primary)
iren 8-K exhibit (irenreportsq3fy26results.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗
Quote: “2026 expansion to 480MW on track o Horizon 1-4 on track for delivery by year-end o Operational capacity fully contracted”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenreportsq3fy26results.htm)
Quote: “2026 expansion to 480MW on track o Horizon 1-4 on track for delivery by year-end o Operational capacity fully contracted”