2026 Capacity Expansion to 480MW
Company: IREN - Project: Childress
The claim, verbatim
Horizon 1-4 data center deployment at Childress on track for delivery by year-end 2026 with 480MW capacity, fully contracted
Source (primary)
iren 8-K exhibit (irenreportsq3fy26results.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-08)Live source ↗
Quote: “2026 expansion to 480MW on track o Horizon 1-4 on track for delivery by year-end o Operational capacity fully contracted”
How we checked this
Checked on September 19, 2026. The cited source supports every part of this claim.
The highlights confirm the 480MW 2026 expansion, Horizon 1-4 year-end delivery, and fully contracted status, and management commentary places Horizon 1-4 at Childress.
Confirmed in the source:
- IREN's 2026 expansion to 480MW is on track
- Horizon 1-4 is on track for delivery by year-end
- Horizon 1-4 data centers are located at Childress
- Operational capacity is fully contracted
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884826000025/irenreportsq3fy26results.htm) in full (30,392 characters, retrieved September 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (irenreportsq3fy26results.htm)
Quote: “2026 expansion to 480MW on track o Horizon 1-4 on track for delivery by year-end o Operational capacity fully contracted”