Childress Horizon liquid-cooled data centers for Microsoft

Company: IREN - Project: Childress

Subject kind
facility capacity
Statement date
2025-11-05
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

IREN is accelerating construction of Horizon 1-4 liquid-cooled data centers at Childress with 200MW critical IT load, featuring Tier 3-equivalent concurrent maintainability, 100MW superclusters for high-performance training, and flexible rack densities of 130-200kW.

Source (primary)

iren 8-K exhibit (q1fy26resultspressreleas.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-27)Live source ↗

Quote: “Accelerating construction of Horizon 1-4 (200MW critical IT load) liquid-cooled data centers for Microsoft. Significant enhancements to original Horizon design, including Tier 3-equivalent concurrent maintainability, 100MW superclusters for high-performance training, and flexible rack densities (130-200kW).”

How we checked this

Checked on September 29, 2026. The cited source supports every part of this claim.

The Childress project update states each of these points. It also says the Horizon 1-4 data centers are being built for Microsoft.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000079/q1fy26resultspressreleas.htm) in full (25,079 characters, retrieved September 27, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (q1fy26resultspressreleas.htm)

Quote: “Accelerating construction of Horizon 1-4 (200MW critical IT load) liquid-cooled data centers for Microsoft. Significant enhancements to original Horizon design, including Tier 3-equivalent concurrent maintainability, 100MW superclusters for high-performance training, and flexible rack densities (130-200kW).”

View cached copy (2026-09-27)Live source ↗