jain.com

Childress, Texas site expansion to 650MW

Company: IREN - Project: Childress

Subject kind
facility capacity
Statement date
2025-05-13
Promised by
2025-06-30
Promised amount
650.0 MW
Current status
verified

What the later record shows

Delivered on time · happened June 30, 2025

The 10-K states that Childress had approximately 650MW of operating data center capacity as of June 30, 2025, matching the assumed increase to 650MW by that date.

“as of June 30, 2025, has approximately 650MW of operating data center capacity and installed hashrate capacity of approximately 40.1 EH/s”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗

Checked October 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The Childress, Texas site had 500MW of installed nameplate capacity as at 31 March 2025, which the company assumes will increase incrementally to 650MW by 30 June 2025.

Source (primary)

iren 8-K exhibit (iren-20250331_d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-15)Live source ↗

Quote: “Expansion of operations at the Childress site, Texas with installed nameplate capacity of 500MW as at 31 March 2025 incrementally increasing to 650MW by 30 June 2025”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The going-concern note lists, as a key assumption in the company's 12-month cash flow forecast, 500MW of installed nameplate capacity at Childress as at 31 March 2025, increasing incrementally to 650MW by 30 June 2025.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000043/iren-20250331_d2.htm) in full (68,582 characters, retrieved October 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (iren-20250331_d2.htm)

Quote: “Expansion of operations at the Childress site, Texas with installed nameplate capacity of 500MW as at 31 March 2025 incrementally increasing to 650MW by 30 June 2025”

View cached copy (2026-10-15)Live source ↗

confirms IREN 10-K filed 2025-08-28

Quote: “as of June 30, 2025, has approximately 650MW of operating data center capacity and installed hashrate capacity of approximately 40.1 EH/s”

View cached copy (2026-08-31)Live source ↗

Record of changes

October 15, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 15, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.