Childress Phase 4-5 (300MW) in H1 2025
Company: IREN
What the later record shows
Delivered on time · happened June 29, 2025
Phase 4 was energized by March 2025, which brought Childress to 500MW. By June 29, 2025, Childress supported 650MW operating, so Phase 5 was also done within H1 2025.
“Phase 4 (150MW) energized, with site operating data centers increased to 500MW”
2025-04-03 · iren 8-K exhibit (pressreleasemarch2025mon.htm) View cached copy (2026-10-17)Live source ↗
“The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗
Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phases 4-5, adding 300MW (20 EH/s), are under construction with expected completion in H1 2025.
Source (primary)
iren 8-K exhibit (nov2024monthlyupdatevdc.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗
Quote: “Childress Phase 4 - 5 (Texas, USA) 300 20 H1 2025 Under construction”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)
Quote: “Childress Phase 4 - 5 (Texas, USA) 300 20 H1 2025 Under construction”
confirms iren 8-K exhibit (a50ehsupdate_vff.htm)
Quote: “The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”
confirms iren 8-K exhibit (pressreleasemarch2025mon.htm)
Quote: “Phase 4 (150MW) energized, with site operating data centers increased to 500MW”