Childress Phase 4-5 (300MW) in H1 2025

Company: IREN

Subject kind
facility timeline
Statement date
2024-12-05
Promised by
2025-06-30
Promised amount
300.0 MW
Current status
verified

What the later record shows

Delivered on time · happened June 29, 2025

Phase 4 was energized by March 2025, which brought Childress to 500MW. By June 29, 2025, Childress supported 650MW operating, so Phase 5 was also done within H1 2025.

“Phase 4 (150MW) energized, with site operating data centers increased to 500MW”
2025-04-03 · iren 8-K exhibit (pressreleasemarch2025mon.htm) View cached copy (2026-10-17)Live source ↗
“The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗

Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Childress Phases 4-5, adding 300MW (20 EH/s), are under construction with expected completion in H1 2025.

Source (primary)

iren 8-K exhibit (nov2024monthlyupdatevdc.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗

Quote: “Childress Phase 4 - 5 (Texas, USA) 300 20 H1 2025 Under construction”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)

Quote: “Childress Phase 4 - 5 (Texas, USA) 300 20 H1 2025 Under construction”

View cached copy (2026-10-24)Live source ↗

confirms iren 8-K exhibit (a50ehsupdate_vff.htm)

Quote: “The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”

View cached copy (2026-10-11)Live source ↗

confirms iren 8-K exhibit (pressreleasemarch2025mon.htm)

Quote: “Phase 4 (150MW) energized, with site operating data centers increased to 500MW”

View cached copy (2026-10-17)Live source ↗

Record of changes

October 24, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 24, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.