Childress Phase 3 (150MW) completion
Company: IREN
What the later record shows
Delivered on time · happened December 31, 2024
In early December, 4 of the 6 Phase 3 buildings were complete. By December month-end, Childress showed 350MW complete and operating (100+100+150MW) and Phase 3 no longer appeared as under construction.
“4 data center buildings complete, energized and hashing”
2024-12-05 · iren 8-K exhibit (nov2024monthlyupdatevdc.htm) View cached copy (2026-10-24)Live source ↗
“Data center expansion: 17x expansion at Childress from 20MW to 350MW”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
“Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
Checked November 1, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 3, a 150MW expansion adding 10 EH/s, is under construction and scheduled for 4Q 2024; mass grading for the substation is complete.
Source (primary)
iren 8-K exhibit (junemonthlyinvestorupdat.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-01)Live source ↗
Quote: “Childress Phase 3 (150MW) – 4Q 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (junemonthlyinvestorupdat.htm)
Quote: “Childress Phase 3 (150MW) – 4Q 2024”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “Data center expansion: 17x expansion at Childress from 20MW to 350MW”
confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)
Quote: “4 data center buildings complete, energized and hashing”