Childress 80MW data center expansion delivery

Company: IREN - Project: Childress

This claim was marked delayed on September 4, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2023-12-14
Promised by
2024-06-30
Promised amount
80.0 MW
Current status
delayed

The claim, verbatim

80MW data center expansion at Childress to be progressively delivered from January 2024 through Q2 2024

Source (primary)

IREN 6-K filed 2023-12-15 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The Company's 80MW data center expansion at Childress remains on track to be progressively delivered from January 2024 through to Q2 2024”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms IREN 6-K filed 2023-12-15

Quote: “The Company's 80MW data center expansion at Childress remains on track to be progressively delivered from January 2024 through to Q2 2024”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.