50 EH/s expansion accelerated to H1 2025
Company: IREN
What the later record shows
Outcome not yet confirmed
The February 2025 release calls the 50 EH/s expansion on track for H1 2025, and the March 2025 report repeats the target. No passage confirms 50 EH/s was reached.
“o 31 EH/s installed o 50 EH/s expansion on-track for H1 2025”
2025-02-11 · iren 8-K exhibit (q2fy25resultspressreleas.htm) View cached copy (2026-10-20)Live source ↗
“targeting 650MW to support our hashrate expansion to 50 EH/s in the first half of 2025”
2025-05-13 · iren 8-K exhibit (irenlimited-exx994mar2025.htm) View cached copy (2026-10-15)Live source ↗
Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN pulled its expansion to 50 EH/s forward to H1 2025, from H2 2025 previously, through a single-site expansion at Childress.
Source (primary)
iren 8-K exhibit (ex991resultspressrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗
Quote: “Accelerating expansion to 50 EH/s in H1 2025 o Previously H2 2025 o Single site expansion at Childress”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ex991resultspressrelease.htm)
Quote: “Accelerating expansion to 50 EH/s in H1 2025 o Previously H2 2025 o Single site expansion at Childress”