Childress additional 100MW for H2 2025
Company: IREN
What the later record shows
Outcome not yet confirmed
The later 'H2 2025 (100MW)' increment was re-scoped to Horizon 1 (50MW IT load / 75MW), which was still under construction as of June 30, 2025. No passage says it, or a 910MW total, was reached; the February 2026 10-Q still describes the expansion as underway.
“Childress Horizon 1 (Texas, USA) 75 N/A Under construction”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗
“We are currently undertaking an expansion of our data center capacity at Childress to support direct-to-chip liquid cooling GPU deployments known as “Horizon 1,””
2026-02-04 · IREN 10-Q filed 2026-02-05 View cached copy (2026-08-31)Live source ↗
Checked October 18, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
At Childress, a further 100MW of capacity is under construction for H2 2025, taking total data center capacity to 910MW.
Source (primary)
iren 8-K exhibit (irenfebmonthlyupdatevf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-18)Live source ↗
Quote: “H2 2025 (100MW)”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenfebmonthlyupdatevf.htm)
Quote: “H2 2025 (100MW)”