50MW data center capacity construction at Childress in 2024

Company: IREN - Project: Childress

Subject kind
facility capacity
Statement date
2024-05-14
Promised by
2024-12-31
Promised amount
50.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

Childress had about 100 MW in mid-2024 with Phases 2 and 3 under construction, and about 650 MW operating by June 30, 2025, so the additional capacity was built. No passage says whether the extra 50MW was finished within 2024.

“construction of Childress Phase 2 (additional 100MW) and Phase 3 (additional 150MW) which is well underway”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗
“as of June 30, 2025, has approximately 650MW of operating data center capacity and installed hashrate capacity of approximately 40.1 EH/s”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction of an additional 50MW of data center capacity at Childress in 2024

Source (primary)

IREN 6-K filed 2024-05-15 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “along with the construction of an additional 50MW of data center capacity at Childress in 2024”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The 6-K says the expanded growth plan is enabled in part by building an additional 50MW of data center capacity at Childress in 2024.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1878848/000114036124026268/ef20027345_6k.htm) in full (15,411 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms IREN 6-K filed 2024-05-15

Quote: “along with the construction of an additional 50MW of data center capacity at Childress in 2024”

View cached copy (2026-08-31)Live source ↗

confirms IREN 20-F filed 2024-08-28

Quote: “construction of Childress Phase 2 (additional 100MW) and Phase 3 (additional 150MW) which is well underway”

View cached copy (2026-08-31)Live source ↗

confirms IREN 10-K filed 2025-08-28

Quote: “as of June 30, 2025, has approximately 650MW of operating data center capacity and installed hashrate capacity of approximately 40.1 EH/s”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.