Childress Phase 1 remaining 15MW by May 2024
Company: IREN
What the later record shows
Delivered; the record does not say when
The update published on 2024-07-04 lists the full 100MW of Childress Phase 1 as complete and operating, and the 20-F shows it operating as of June 30, 2024. Neither says whether the final 15MW was finished by the end of May 2024.
“Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating”
2024-07-04 · iren 8-K exhibit (junemonthlyinvestorupdat.htm) View cached copy (2026-11-01)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Operating Total Operating 260 10.0”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗
Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The remaining 15MW of Childress Phase 1 is under construction with May 2024 timing, adding 0.6 EH/s and completing the first 100MW.
Source (primary)
iren 8-K exhibit (ef20028541_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-06)Live source ↗
Quote: “Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ef20028541_ex99-1.htm)
Quote: “Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”
confirms IREN 20-F filed 2024-08-28
Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Operating Total Operating 260 10.0”
confirms iren 8-K exhibit (junemonthlyinvestorupdat.htm)
Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating”