Childress 80MW expansion delivery start

Company: IREN - Project: Childress

Subject kind
facility timeline
Statement date
2024-01-04
Promised by
2024-01-31
Promised amount
80.0 MW
Current status
verified

What the later record shows

Delivered late · happened June 30, 2024

The Childress Phase 1 build-out was 85MW operating in May 2024 and the full 100MW was operating by June 30, 2024. Operating hashrate reached 10 EH/s around early June 2024, after the January 2024 start date.

“Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”
2024-05-05 · iren 8-K exhibit (ef20028541_ex99-1.htm) View cached copy (2026-11-06)Live source ↗
“Average operating hashrate of 9.4 EH/s (now expanded to 10 EH/s)”
2024-06-05 · iren 8-K exhibit (ef20030723_ex99-1.htm) View cached copy (2026-11-04)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Operating Total Operating 260 10.0”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗

Checked November 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The 80MW expansion at Childress will be delivered progressively starting January 2024, supporting an increase in operating hashrate from 5.6 EH/s to 10 EH/s.

Source (primary)

iren 8-K exhibit (ef20018183_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗

Quote: “80MW expansion at Childress to be delivered progressively from January 2024, supporting the increase in operating hashrate from 5.6 EH/s to 10 EH/s”

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036124000809/ef20018183_ex99-1.htm) in full (19,930 characters, retrieved November 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (ef20018183_ex99-1.htm)

Quote: “80MW expansion at Childress to be delivered progressively from January 2024, supporting the increase in operating hashrate from 5.6 EH/s to 10 EH/s”

View cached copy (2026-11-15)Live source ↗

confirms IREN 20-F filed 2024-08-28

Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Operating Total Operating 260 10.0”

View cached copy (2026-08-31)Live source ↗

confirms iren 8-K exhibit (ef20030723_ex99-1.htm)

Quote: “Average operating hashrate of 9.4 EH/s (now expanded to 10 EH/s)”

View cached copy (2026-11-04)Live source ↗

confirms iren 8-K exhibit (ef20028541_ex99-1.htm)

Quote: “Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”

View cached copy (2026-11-06)Live source ↗

Record of changes

November 15, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 15, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 15, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.