Childress Phase 1 80MW expansion to 9.4 EH/s in early 2024
Company: IREN
What the later record shows
Delivered late · happened May 14, 2024
Delivery began in early 2024, but only 40MW of the 80MW expansion was operating by March 29, 2024. Childress reached 100MW and total capacity reached about 260MW by May 14, 2024, after the 'early 2024' (end of Q1) date.
“Childress Phase 1 (first 100MW) – H1 2024 o Supports expansion to 10 EH/s o 60MW operating, 40MW under construction”
2024-04-03 · iren 8-K exhibit (ef20026073_ex99-1.htm) View cached copy (2026-11-08)Live source ↗
“Childress Phase 1 (Texas, USA) 85 4.2 Complete Operating Total Operating 245 9.4”
2024-05-05 · iren 8-K exhibit (ef20028541_ex99-1.htm) View cached copy (2026-11-06)Live source ↗
“As of May 14, 2024, we have approximately 260MW of data center capacity and hashrate capacity of approximately 10 EH/s across our sites in BC (160MW) and Texas (100MW).”
2024-05-14 · iren 8-K exhibit (ef20027345_ex99-4.htm) View cached copy (2026-11-05)Live source ↗
Checked November 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The 80MW under construction at Childress (Phase 1) remains on track. The company gives indicative timing of early 2024 for commencement of data center delivery, taking total capacity to 260MW and 9.4 EH/s.
Source (primary)
iren 8-K exhibit (ef20014192_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗
Quote: “Childress (Texas, USA) 80 3.8 6 Early 2024 10 Under construction Total (Canada & USA) 260 9.4”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ef20014192_ex99-1.htm)
Quote: “Childress (Texas, USA) 80 3.8 6 Early 2024 10 Under construction Total (Canada & USA) 260 9.4”
confirms iren 8-K exhibit (ef20027345_ex99-4.htm)
Quote: “As of May 14, 2024, we have approximately 260MW of data center capacity and hashrate capacity of approximately 10 EH/s across our sites in BC (160MW) and Texas (100MW).”
confirms iren 8-K exhibit (ef20028541_ex99-1.htm)
Quote: “Childress Phase 1 (Texas, USA) 85 4.2 Complete Operating Total Operating 245 9.4”
confirms iren 8-K exhibit (ef20026073_ex99-1.htm)
Quote: “Childress Phase 1 (first 100MW) – H1 2024 o Supports expansion to 10 EH/s o 60MW operating, 40MW under construction”