Childress data center minimum 200 MW capacity

Company: IREN

Subject kind
facility capacity
Statement date
2022-03-14
Promised by
2025-12-31
Promised amount
200.0 MW
Current status
verified

What the later record shows

Delivered on time · happened March 31, 2025

Childress had 500 MW of data center capacity as of March 31, 2025, and 650 MW by September 30, 2025. Both are well above the 200 MW minimum and before the December 31, 2025 deadline.

“Our 750MW site in Childress has been operating since April 2023 and, as of March 31, 2025, had 500MW of data center capacity”
2025-05-13 · iren 8-K exhibit (irenlimited-exx994mar2025.htm) View cached copy (2026-10-15)Live source ↗
“Our 750MW Childress site has been operating since April 2023 and, as of September 30, 2025, has approximately 650MW of operating data center capacity”
2025-11-05 · IREN 10-Q filed 2025-11-06 View cached copy (2026-08-31)Live source ↗

Checked October 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Owner (IREN subsidiaries) agreed its Childress County data center facility in the Iris Energy Reinvestment Zone will have a minimum Data Center Capacity of no less than 200 MW (AC), and the abatement is conditioned on capacity not falling below that minimum.

Source (primary)

Childress County TX tax abatement - US IE Hardware- Phase 3 (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗

Quote: “Owner agrees that its data center facility on the Site in the Reinvestment Zone will have a minimum Data Center Capacity of no less than two hundred (200) megawatts (AC).”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Childress County TX tax abatement - US IE Hardware- Phase 3

Quote: “Owner agrees that its data center facility on the Site in the Reinvestment Zone will have a minimum Data Center Capacity of no less than two hundred (200) megawatts (AC).”

View cached copy (2026-10-17)Live source ↗

confirms IREN 10-Q filed 2025-11-06

Quote: “Our 750MW Childress site has been operating since April 2023 and, as of September 30, 2025, has approximately 650MW of operating data center capacity”

View cached copy (2026-08-31)Live source ↗

confirms iren 8-K exhibit (irenlimited-exx994mar2025.htm)

Quote: “Our 750MW site in Childress has been operating since April 2023 and, as of March 31, 2025, had 500MW of data center capacity”

View cached copy (2026-10-15)Live source ↗

Record of changes

October 17, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 17, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.