Childress Phase 2 & 3 (200MW) completion H2 2024

Company: IREN - Project: Childress

Subject kind
facility timeline
Statement date
2024-04-03
Promised by
2024-12-31
Promised amount
200.0 MW
Current status
verified

What the later record shows

Delivered on time · happened December 31, 2024

Phase 3 was upsized to 150MW and was complete by December 2024, with all six 25MW buildings energized. Childress operating capacity reached 350MW, which covers Phases 1 through 3, including Phase 2's 100MW.

“6 x 25MW data center buildings now complete, energized and hashing”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
“Installed self-mining capacity increased to 31 EH/s during the month following completion of Childress Phase 3”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗

Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Childress Phases 2 and 3 (next 200MW) are scheduled for H2 2024, supporting expansion to 20 EH/s; construction is underway with about 180 personnel on site.

Source (primary)

iren 8-K exhibit (ef20026073_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗

Quote: “Childress Phase 2 & 3 (next 200MW) – H2 2024 o Supports expansion to 20 EH/s o Construction underway with ~180 personnel on site”

How we checked this

Checked on November 10, 2026. The cited source supports every part of this claim.

The investor update states every element of this claim: 200MW for H2 2024, support for expansion to 20 EH/s, and construction underway with about 180 personnel on site.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036124017811/ef20026073_ex99-1.htm) in full (16,971 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (ef20026073_ex99-1.htm)

Quote: “Childress Phase 2 & 3 (next 200MW) – H2 2024 o Supports expansion to 20 EH/s o Construction underway with ~180 personnel on site”

View cached copy (2026-11-08)Live source ↗

confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)

Quote: “6 x 25MW data center buildings now complete, energized and hashing”

View cached copy (2026-10-21)Live source ↗

Record of changes

November 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 8, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.