Delivered; the record does not say when
Childress had about 650MW of operating capacity as of September 30, 2025, and 810MW total was operating by July 2, 2025. Neither passage states the date Childress reached 650MW, so on-time delivery by June 30 cannot be confirmed.
“Next-Generation Data Centers : 810MW of operating data centers underpinning three verticals: Bitcoin Mining, AI Cloud Services and AI Data Centers.”
2025-07-02 · iren 8-K exhibit (ef20051566_ex99-1.htm) View cached copy (2026-10-11)Live source ↗
“Our 750MW Childress site has been operating since April 2023 and, as of September 30, 2025, has approximately 650MW of operating data center capacity”
2025-11-05 · IREN 10-Q filed 2025-11-06 View cached copy (2026-08-31)Live source ↗
Checked October 18, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN is expanding data center capacity at Childress, Texas, targeting 650MW in the first half of 2025 to support hashrate expansion to 50 EH/s.
Source (primary)
iren 8-K exhibit (irenlimited-exx992dec2024x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-18)Live source ↗
Quote: “We are currently undertaking an expansion of our data center capacity at Childress, targeting 650MW to support expansion to 50 EH/s of our hashrate in the first half of 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenlimited-exx992dec2024x.htm)
Quote: “We are currently undertaking an expansion of our data center capacity at Childress, targeting 650MW to support expansion to 50 EH/s of our hashrate in the first half of 2025”
confirms IREN 10-Q filed 2025-11-06
Quote: “Our 750MW Childress site has been operating since April 2023 and, as of September 30, 2025, has approximately 650MW of operating data center capacity”
confirms iren 8-K exhibit (ef20051566_ex99-1.htm)