Childress Phase 3 (150MW) 4Q 2024
Company: IREN
What the later record shows
Delivered on time · happened December 31, 2024
Childress reached 350MW by year-end 2024, which is Phases 1-2 (200MW) plus Phase 3 (150MW). Total capacity also rose from 360MW to 510MW. Phase 3 is not named as complete, so this rests on the arithmetic.
“Data center expansion: 17x expansion at Childress from 20MW to 350MW”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
“Childress (750MW) • Phase 1-4 (500MW) now fully operational • Phase 5 (150MW) structures nearing completion”
2025-05-05 · iren 8-K exhibit (aprilmonthlyupdatevf.htm) View cached copy (2026-10-16)Live source ↗
Checked October 26, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 3, a 150MW expansion, is targeted for 4Q 2024, with structural and electrical works ongoing.
Source (primary)
iren 8-K exhibit (irensepmonthlyupdate4oct.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-26)Live source ↗
Quote: “Childress Phase 3 (150MW): 4Q 2024 o Structural and electrical works ongoing”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irensepmonthlyupdate4oct.htm)
Quote: “Childress Phase 3 (150MW): 4Q 2024 o Structural and electrical works ongoing”
confirms iren 8-K exhibit (aprilmonthlyupdatevf.htm)
Quote: “Childress (750MW) • Phase 1-4 (500MW) now fully operational • Phase 5 (150MW) structures nearing completion”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “Data center expansion: 17x expansion at Childress from 20MW to 350MW”