Childress Phases 4-6 expansion 2025+

Company: IREN

Subject kind
facility timeline
Statement date
2024-10-03
Promised amount
400.0 MW
Current status
stated

The claim, verbatim

Childress Phases 4 to 6 (300MW for Phases 4-5 plus 100MW for Phase 6) are a 2025+ expansion. Civil works and procurement of long-lead items are ongoing.

Source (primary)

iren 8-K exhibit (irensepmonthlyupdate4oct.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-26)Live source ↗

Quote: “Childress Phase 4 – 6: 2025+ expansion o Civil works and procurement of long lead items ongoing”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (irensepmonthlyupdate4oct.htm)

Quote: “Childress Phase 4 – 6: 2025+ expansion o Civil works and procurement of long lead items ongoing”

View cached copy (2026-10-26)Live source ↗