Childress Phase 1 estimated capital investment
Company: IREN
The claim, verbatim
If built to maximum capacity, the Childress data center is estimated to require a capital investment of about $197.5 million.
Source (primary)
Childress County TX tax abatement - US IE Hardware- Phase 1 (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗
Quote: “will require an estimated capital investment of approximately one hundred ninety-seven million five hundred thousand dollars ($197,500,000.00)”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Childress County TX tax abatement - US IE Hardware- Phase 1