jain.com

Childress retrofit GPU delivery

Company: IREN - Project: Childress

This claim was marked delayed on September 8, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2026-05-10
Promised by
2026-07-01
Promised amount
50.0 MW
Current status
delayed

The claim, verbatim

Initial 50 megawatts of data center retrofits at Childress with GPU deliveries in H2 2026

Source (primary)

iren 8-K exhibit (irentranscript.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-07)Live source ↗

Quote: “at Childress, data center retrofits are underway across an initial 50 megawatts ahead of GPU deliveries in the second half of this year.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (irentranscript.htm)

Quote: “at Childress, data center retrofits are underway across an initial 50 megawatts ahead of GPU deliveries in the second half of this year.”

View cached copy (2026-09-07)Live source ↗

Record of changes

September 7, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 8, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.