Childress Phase 3 (150MW) in 4Q CY24

Company: IREN

Subject kind
facility timeline
Statement date
2024-08-27
Promised by
2024-12-31
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered on time · happened December 31, 2024

The December 2024 update states that Childress Phase 3 is complete, with all six 25MW buildings energized and hashing, bringing Childress to 350MW.

“4 data center buildings complete, energized and hashing • 2 data center buildings remaining with progressive completion expected this month”
2024-12-05 · iren 8-K exhibit (nov2024monthlyupdatevdc.htm) View cached copy (2026-10-24)Live source ↗
“6 x 25MW data center buildings now complete, energized and hashing”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗

Checked October 30, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Childress Phase 3, a 150MW expansion comprising 6 x 25MW data centers, is scheduled for 4Q CY24, with foundational, structural and electrical works ongoing.

Source (primary)

iren 8-K exhibit (fy24resultspressreleasev.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-30)Live source ↗

Quote: “Childress Phase 3 (150MW, 4Q CY24) – Foundational, structural and electrical works ongoing for 6 x 25MW data centers”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (fy24resultspressreleasev.htm)

Quote: “Childress Phase 3 (150MW, 4Q CY24) – Foundational, structural and electrical works ongoing for 6 x 25MW data centers”

View cached copy (2026-10-30)Live source ↗

confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)

Quote: “6 x 25MW data center buildings now complete, energized and hashing”

View cached copy (2026-10-21)Live source ↗

confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)

Quote: “4 data center buildings complete, energized and hashing • 2 data center buildings remaining with progressive completion expected this month”

View cached copy (2026-10-24)Live source ↗

Record of changes

October 30, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 30, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.