Childress Phase 1 data center construction status

Company: IREN

Subject kind
facility timeline
Statement date
2023-11-06
Current status
stated

The claim, verbatim

At Childress, DC 1 has operated since April 2023. DC 2 structure is complete, with racking and electrical work commenced. DC 3 framing has commenced, DC 4 foundations have commenced, and DC 5 earthworks are complete.

Source (primary)

iren 8-K exhibit (ef20014192_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-17)Live source ↗

Quote: “DC 2: structure and internal framing complete; racking and electrical installation commenced • DC 3: structure and internal framing commenced • DC 4: concrete foundations commenced • DC 5: earthworks complete”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (ef20014192_ex99-1.htm)

Quote: “DC 2: structure and internal framing complete; racking and electrical installation commenced • DC 3: structure and internal framing commenced • DC 4: concrete foundations commenced • DC 5: earthworks complete”

View cached copy (2026-11-17)Live source ↗