jain.com

Childress direct-to-chip liquid cooling up to 50MW IT load

Company: IREN - Project: Childress

Subject kind
facility capacity
Statement date
2025-05-13
Promised amount
50.0 MW
Current status
stated

The claim, verbatim

IREN plans a direct-to-chip liquid cooling deployment at Childress to support an IT load of up to 50MW, based on 200kW rack density and subject to customer requirements, for HPC opportunities.

Source (primary)

iren 8-K exhibit (irenlimited-exx994mar2025.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-15)Live source ↗

Quote: “a direct-to-chip liquid cooling deployment to support an IT load of up to 50MW (based on rack density of 200kW, subject to customer requirements)”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The filing describes a direct-to-chip liquid cooling deployment at Childress supporting up to 50MW of IT load, based on 200kW rack density and subject to customer requirements, for potential HPC opportunities.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000043/irenlimited-exx994mar2025.htm) in full (129,213 characters, retrieved October 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (irenlimited-exx994mar2025.htm)

Quote: “a direct-to-chip liquid cooling deployment to support an IT load of up to 50MW (based on rack density of 200kW, subject to customer requirements)”

View cached copy (2026-10-15)Live source ↗