Childress Phases 2-3 250MW in H2 2024

Company: IREN

Subject kind
facility timeline
Statement date
2024-05-05
Promised by
2024-12-31
Promised amount
250.0 MW
Current status
verified

What the later record shows

Delivered on time · happened December 31, 2024

Childress rose from 100MW operating after Phase 1 to 350MW complete and operating in the December 2024 update published on 2025-01-06, which accounts for the 250MW of Phases 2 and 3. The year-end date is inferred from that update, which gives no exact completion date.

“Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating”
2024-07-04 · iren 8-K exhibit (junemonthlyinvestorupdat.htm) View cached copy (2026-11-01)Live source ↗
“Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗

Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Childress Phases 2 and 3, totalling the next 250MW and more than 10 EH/s of capacity, are under construction with H2 2024 timing.

Source (primary)

iren 8-K exhibit (ef20028541_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-06)Live source ↗

Quote: “Childress Phase 2-3 (Texas USA) 250 >10.0 H2 2024 Under construction”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (ef20028541_ex99-1.htm)

Quote: “Childress Phase 2-3 (Texas USA) 250 >10.0 H2 2024 Under construction”

View cached copy (2026-11-06)Live source ↗

confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)

Quote: “Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”

View cached copy (2026-10-21)Live source ↗

confirms iren 8-K exhibit (junemonthlyinvestorupdat.htm)

Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating”

View cached copy (2026-11-01)Live source ↗

Record of changes

November 6, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 6, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.