Childress 80MW expansion delivery
Company: IREN - Project: Childress
What the later record shows
Delivered on time · happened June 30, 2024
Childress Phase 1 (first 100MW, supporting 10 EH/s) had 85MW operating in May 2024, with the last 15MW due that month. The 20-F/A says Childress had about 100MW of data center capacity as of June 30, 2024, which is within the Q2 2024 target. Medium confidence because no passage explicitly links the 80MW expansion to the Phase 1 100MW total.
“Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”
2024-05-05 · iren 8-K exhibit (ef20028541_ex99-1.htm) View cached copy (2026-11-06)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10.5”
2024-08-05 · iren 8-K exhibit (irenjuly2024monthlyupdat.htm) View cached copy (2026-10-31)Live source ↗
“as of June 30, 2024, has approximately 100 MW of data center capacity and hashrate capacity of approximately 4.8 EH/s”
2025-03-19 · IREN 20-F/A filed 2025-03-20 View cached copy (2026-08-31)Live source ↗
Checked November 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The 80MW data center expansion at Childress is on track to be delivered progressively from January 2024 through Q2 2024, supporting an increase in total operating capacity to 10 EH/s.
Source (primary)
iren 8-K exhibit (ef20016123_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗
Quote: “The Company's 80MW data center expansion at Childress remains on track to be progressively delivered from January 2024 through to Q2 2024, supporting an increase in total Company operating capacity to 10 EH/s”
How we checked this
Additional evidence
confirms iren 8-K exhibit (ef20016123_ex99-1.htm)
Quote: “The Company's 80MW data center expansion at Childress remains on track to be progressively delivered from January 2024 through to Q2 2024, supporting an increase in total Company operating capacity to 10 EH/s”
confirms IREN 20-F/A filed 2025-03-20
Quote: “as of June 30, 2024, has approximately 100 MW of data center capacity and hashrate capacity of approximately 4.8 EH/s”
confirms iren 8-K exhibit (irenjuly2024monthlyupdat.htm)
Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10.5”
confirms iren 8-K exhibit (ef20028541_ex99-1.htm)
Quote: “Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”