Childress Phase 2 completion
Company: IREN
What the later record shows
Delivered on time · happened September 30, 2024
In early September, Childress had 140MW operating and 60MW of Phase 2 under construction for Sep 2024. As of September 30, 2024, Childress had 200MW of data center capacity, so the full 100MW Phase 2 was complete.
“Childress Phase 2 (Texas, USA) 60 2.2 Sep 2024 Under construction”
2024-09-04 · iren 8-K exhibit (irenaug2024monthlyupdate.htm) View cached copy (2026-10-29)Live source ↗
“It has been operating since April 2023 and, as of September 30, 2024, has 200MW of data center capacity”
2025-03-19 · iren 8-K exhibit (irenlimited-exx992sep2024x.htm) View cached copy (2026-10-18)Live source ↗
Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 2 (100MW), comprising 4 x 25MW data centers, is on track for completion by the end of September 2024.
Source (primary)
iren 8-K exhibit (irenjuly2024monthlyupdat.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗
Quote: “4 x 25MW data centers on track for completion by the end of next month”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenjuly2024monthlyupdat.htm)
Quote: “4 x 25MW data centers on track for completion by the end of next month”
confirms iren 8-K exhibit (irenlimited-exx992sep2024x.htm)
Quote: “It has been operating since April 2023 and, as of September 30, 2024, has 200MW of data center capacity”
confirms iren 8-K exhibit (irenaug2024monthlyupdate.htm)
Quote: “Childress Phase 2 (Texas, USA) 60 2.2 Sep 2024 Under construction”