Childress Phase 2 potential to ~13.6 EH/s
Company: IREN
The claim, verbatim
Long-lead items have been ordered for Childress Phase 2 (second 100MW), which has the potential to unlock up to ~13.6 EH/s for the company.
Source (primary)
iren 8-K exhibit (brhc20055660_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-22)Live source ↗
Quote: “Additional long-lead items continue to be ordered for Phase 2 (second 100MW), which has the potential to unlock up to ~13.6 EH/s 4 for the Company.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (brhc20055660_ex99-1.htm)
Quote: “Additional long-lead items continue to be ordered for Phase 2 (second 100MW), which has the potential to unlock up to ~13.6 EH/s 4 for the Company.”