jain.com

Horizon 1 delivered at Childress

Company: IREN - Project: Childress

Subject kind
facility capacity
Statement date
2026-11-04
Promised amount
50.0 MW
Current status
stated

The claim, verbatim

IREN delivered Horizon 1, a 50 MW liquid-cooled deployment, at its Childress campus.

Source (primary)

IREN Falls 5%, CoreWeave Drops 4% as Texas Election Stokes Data Center Moratorium Fears; Nebius Dips 2% - 24/7 Wall St. (-, news_article)
View cached copy (2026-11-05)Live source ↗Archive.org ↗

Quote: “IREN delivered Horizon 1, a 50-megawatt (MW) liquid-cooled deployment, at its Childress campus”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms IREN Falls 5%, CoreWeave Drops 4% as Texas Election Stokes Data Center Moratorium Fears; Nebius Dips 2% - 24/7 Wall St.

Quote: “IREN delivered Horizon 1, a 50-megawatt (MW) liquid-cooled deployment, at its Childress campus”

View cached copy (2026-11-05)Live source ↗Archive.org ↗

confirms IREN Falls 5%, CoreWeave Drops 4% as Texas Election Stokes Data Center Moratorium Fears; Nebius Dips 2% - Yahoo Finance

Quote: “IREN delivered Horizon 1, a 50-megawatt (MW) liquid-cooled deployment, at its Childress campus”

View cached copy (2026-11-05)Live source ↗Archive.org ↗