Childress Phase 1 remaining 40MW in H1 2024
Company: IREN - Project: Childress
What the later record shows
Delivered on time · happened June 5, 2024
In May, 85MW of Phase 1 was operating, with the last 15MW due in May. The June 5 update shows 260MW operating, which matches the May figure of 245MW plus 15MW, and the following update lists Childress Phase 1 at 100MW complete and operating.
“Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”
2024-05-05 · iren 8-K exhibit (ef20028541_ex99-1.htm) View cached copy (2026-11-06)Live source ↗
“260MW operating, 510MW in 2024 • Childress Phase 2 & 3 construction progressing to schedule”
2024-06-05 · iren 8-K exhibit (ef20030723_ex99-1.htm) View cached copy (2026-11-04)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10”
2024-07-04 · iren 8-K exhibit (junemonthlyinvestorupdat.htm) View cached copy (2026-11-01)Live source ↗
Checked November 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
At Childress Phase 1, 60MW is energized and the remaining 40MW is to be commissioned in the coming months, targeted for H1 2024.
Source (primary)
iren 8-K exhibit (ef20023430_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-09)Live source ↗
Quote: “60MW energized, 40MW to be commissioned in the coming months”
How we checked this
Checked on November 11, 2026. The cited source supports every part of this claim.
The construction update gives the 60MW and 40MW status, and the capacity table lists the 40MW tranche with H1 2024 timing.
Confirmed in the source:
- At Childress Phase 1, 60MW is energized.
- The remaining 40MW of Childress Phase 1 is to be commissioned in the coming months.
- The 40MW Childress Phase 1 tranche is listed with H1 2024 timing.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036124011575/ef20023430_ex99-1.htm) in full (16,339 characters, retrieved November 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (ef20023430_ex99-1.htm)
Quote: “60MW energized, 40MW to be commissioned in the coming months”
confirms iren 8-K exhibit (junemonthlyinvestorupdat.htm)
Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10”
confirms iren 8-K exhibit (ef20030723_ex99-1.htm)
Quote: “260MW operating, 510MW in 2024 • Childress Phase 2 & 3 construction progressing to schedule”
confirms iren 8-K exhibit (ef20028541_ex99-1.htm)
Quote: “Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”