Childress Phase 1 remaining 40MW in H1 2024

Company: IREN - Project: Childress

Subject kind
facility timeline
Statement date
2024-03-05
Promised by
2024-06-30
Promised amount
40.0 MW
Current status
verified

What the later record shows

Delivered on time · happened June 5, 2024

In May, 85MW of Phase 1 was operating, with the last 15MW due in May. The June 5 update shows 260MW operating, which matches the May figure of 245MW plus 15MW, and the following update lists Childress Phase 1 at 100MW complete and operating.

“Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”
2024-05-05 · iren 8-K exhibit (ef20028541_ex99-1.htm) View cached copy (2026-11-06)Live source ↗
“260MW operating, 510MW in 2024 • Childress Phase 2 & 3 construction progressing to schedule”
2024-06-05 · iren 8-K exhibit (ef20030723_ex99-1.htm) View cached copy (2026-11-04)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10”
2024-07-04 · iren 8-K exhibit (junemonthlyinvestorupdat.htm) View cached copy (2026-11-01)Live source ↗

Checked November 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

At Childress Phase 1, 60MW is energized and the remaining 40MW is to be commissioned in the coming months, targeted for H1 2024.

Source (primary)

iren 8-K exhibit (ef20023430_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-09)Live source ↗

Quote: “60MW energized, 40MW to be commissioned in the coming months”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

The construction update gives the 60MW and 40MW status, and the capacity table lists the 40MW tranche with H1 2024 timing.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036124011575/ef20023430_ex99-1.htm) in full (16,339 characters, retrieved November 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (ef20023430_ex99-1.htm)

Quote: “60MW energized, 40MW to be commissioned in the coming months”

View cached copy (2026-11-09)Live source ↗

confirms iren 8-K exhibit (junemonthlyinvestorupdat.htm)

Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10”

View cached copy (2026-11-01)Live source ↗

confirms iren 8-K exhibit (ef20030723_ex99-1.htm)

Quote: “260MW operating, 510MW in 2024 • Childress Phase 2 & 3 construction progressing to schedule”

View cached copy (2026-11-04)Live source ↗

confirms iren 8-K exhibit (ef20028541_ex99-1.htm)

Quote: “Childress Phase 1 (Texas, USA) 15 0.6 May 2024 Under construction”

View cached copy (2026-11-06)Live source ↗

Record of changes

November 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.