Childress Phase 5 (150MW) construction
Company: IREN - Project: Childress
What the later record shows
Delivered on time · happened June 29, 2025
By June 29, 2025, Childress supported 650MW of operating capacity, up from 500MW, which implies Phase 5's 150MW was online. The July update states Phase 5 is now complete. The exact completion date is not stated, but it was no later than June 29.
“750MW Childress site, now supporting 650MW of operating capacity and forming the foundation”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗
“650MW total operating data centers, with Phase 5 (150MW) now complete”
2025-07-06 · iren 8-K exhibit (ef20051646_ex99-1.htm) View cached copy (2026-10-11)Live source ↗
Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 5 (150MW) structures are nearing completion, with substation transformer installation commencing in the coming weeks; site chart shows 150MW under construction for H1 2025.
Source (primary)
iren 8-K exhibit (aprilmonthlyupdatevf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-16)Live source ↗
Quote: “Phase 5 (150MW) structures nearing completion, with substation transformer installation commencing in coming weeks”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The update describes Phase 5's status in these terms, and its Childress site chart lists 'Under Construction H1 2025 (150MW).'
Confirmed in the source:
- Childress Phase 5 is 150MW
- Phase 5 structures are nearing completion
- Substation transformer installation is commencing in the coming weeks
- The site chart shows 150MW under construction for H1 2025
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000037/aprilmonthlyupdatevf.htm) in full (21,129 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (aprilmonthlyupdatevf.htm)
Quote: “Phase 5 (150MW) structures nearing completion, with substation transformer installation commencing in coming weeks”
confirms iren 8-K exhibit (ef20051646_ex99-1.htm)
Quote: “650MW total operating data centers, with Phase 5 (150MW) now complete”
confirms iren 8-K exhibit (a50ehsupdate_vff.htm)
Quote: “750MW Childress site, now supporting 650MW of operating capacity and forming the foundation”