Childress Phase 5 (150MW) construction

Company: IREN - Project: Childress

Subject kind
facility timeline
Statement date
2025-05-05
Promised by
2025-06-30
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered on time · happened June 29, 2025

By June 29, 2025, Childress supported 650MW of operating capacity, up from 500MW, which implies Phase 5's 150MW was online. The July update states Phase 5 is now complete. The exact completion date is not stated, but it was no later than June 29.

“750MW Childress site, now supporting 650MW of operating capacity and forming the foundation”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗
“650MW total operating data centers, with Phase 5 (150MW) now complete”
2025-07-06 · iren 8-K exhibit (ef20051646_ex99-1.htm) View cached copy (2026-10-11)Live source ↗

Checked October 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Childress Phase 5 (150MW) structures are nearing completion, with substation transformer installation commencing in the coming weeks; site chart shows 150MW under construction for H1 2025.

Source (primary)

iren 8-K exhibit (aprilmonthlyupdatevf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-16)Live source ↗

Quote: “Phase 5 (150MW) structures nearing completion, with substation transformer installation commencing in coming weeks”

How we checked this

Checked on October 17, 2026. The cited source supports every part of this claim.

The update describes Phase 5's status in these terms, and its Childress site chart lists 'Under Construction H1 2025 (150MW).'

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000037/aprilmonthlyupdatevf.htm) in full (21,129 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (aprilmonthlyupdatevf.htm)

Quote: “Phase 5 (150MW) structures nearing completion, with substation transformer installation commencing in coming weeks”

View cached copy (2026-10-16)Live source ↗

confirms iren 8-K exhibit (ef20051646_ex99-1.htm)

Quote: “650MW total operating data centers, with Phase 5 (150MW) now complete”

View cached copy (2026-10-11)Live source ↗

confirms iren 8-K exhibit (a50ehsupdate_vff.htm)

Quote: “750MW Childress site, now supporting 650MW of operating capacity and forming the foundation”

View cached copy (2026-10-11)Live source ↗

Record of changes

October 16, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 16, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.