Childress Phase 3 completion in 4Q 2024
Company: IREN
What the later record shows
Delivered on time · happened December 31, 2024
The December 2024 update said all six 25MW Phase 3 buildings were complete, energized and hashing, which brought Childress to 350MW.
“6 x 25MW data center buildings now complete, energized and hashing”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
“Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 3 (150MW, 6 x 25MW data centers) is scheduled for 4Q 2024; mass grading is complete and foundational, structural and electrical works are ongoing.
Source (primary)
iren 8-K exhibit (irenjuly2024monthlyupdat.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗
Quote: “Childress Phase 3 (150MW) – 4Q 2024 o Mass grading complete o Foundational, structural and electrical works ongoing for 6 x 25MW data centers”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenjuly2024monthlyupdat.htm)
Quote: “Childress Phase 3 (150MW) – 4Q 2024 o Mass grading complete o Foundational, structural and electrical works ongoing for 6 x 25MW data centers”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “6 x 25MW data center buildings now complete, energized and hashing”