Childress 300MW under construction, H1 2025
Company: IREN
What the later record shows
Delivered on time · happened June 29, 2025
Childress had 350MW operating with 300MW under construction for H1 2025. By June 29–30, 2025, Childress had 650MW operating, so the 300MW was finished within H1 2025.
“The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗
“Childress BTC Mining (Texas, USA) 650 40.1 Operating Total Operating 810 50.0”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗
Checked October 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
300MW at Childress is under construction for completion in H1 2025.
Source (primary)
iren 8-K exhibit (janmonthlyupdatevff.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-20)Live source ↗
Quote: “Under Construction H1 2025 (300MW)”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (janmonthlyupdatevff.htm)
Quote: “Under Construction H1 2025 (300MW)”
confirms IREN 10-K filed 2025-08-28
Quote: “Childress BTC Mining (Texas, USA) 650 40.1 Operating Total Operating 810 50.0”
confirms iren 8-K exhibit (a50ehsupdate_vff.htm)
Quote: “The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”