Childress, Texas site capacity ramp to 100MW

Company: IREN

Subject kind
facility capacity
Statement date
2024-02-14
Promised by
2024-06-30
Promised amount
100.0 MW
Current status
verified

What the later record shows

Delivered on time · happened June 5, 2024

The August 2024 update lists Childress Phase 1 (100MW) as complete and operating, within a 260MW operating total. The company already reported 260MW operating on June 5, 2024, which implies the 100MW was reached before June 30, 2024.

“Data Centers Corporate • 260MW operating, 510MW in 2024 • Childress Phase 2 & 3 construction progressing to schedule”
2024-06-05 · iren 8-K exhibit (ef20030723_ex99-1.htm) View cached copy (2026-11-04)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10.5”
2024-08-05 · iren 8-K exhibit (irenjuly2024monthlyupdat.htm) View cached copy (2026-10-31)Live source ↗

Checked November 11, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN's Childress, Texas site has an initial installed nameplate capacity of 20MW, which is expected to increase incrementally to 100MW by 30 June 2024.

Source (primary)

iren 8-K exhibit (ef20015356_ex99-3.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-11)Live source ↗

Quote: “A fourth operational site at Childress, Texas with initial installed nameplate capacity of 20MW incrementally increasing to 100 MW by 30 June 2024.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (ef20015356_ex99-3.htm)

Quote: “A fourth operational site at Childress, Texas with initial installed nameplate capacity of 20MW incrementally increasing to 100 MW by 30 June 2024.”

View cached copy (2026-11-11)Live source ↗

confirms iren 8-K exhibit (irenjuly2024monthlyupdat.htm)

Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10.5”

View cached copy (2026-10-31)Live source ↗

confirms iren 8-K exhibit (ef20030723_ex99-1.htm)

Quote: “Data Centers Corporate • 260MW operating, 510MW in 2024 • Childress Phase 2 & 3 construction progressing to schedule”

View cached copy (2026-11-04)Live source ↗

Record of changes

November 11, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 11, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.