Childress Phase 2-3 (200MW) completion H2 2024
Company: IREN
What the later record shows
Delivered on time · happened December 31, 2024
Childress Phase 2 was operating by the September 2024 update. The December 2024 update shows 350MW at Childress (Phase 1 plus the expanded Phases 2-3) complete and operating at year-end.
“Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”
2024-10-03 · iren 8-K exhibit (irensepmonthlyupdate4oct.htm) View cached copy (2026-10-26)Live source ↗
“Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
Checked November 12, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 2-3 (200MW, 10 EH/s) is under construction, with site civils and procurement underway for completion in H2 2024.
Source (primary)
iren 8-K exhibit (ef20020920_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-12)Live source ↗
Quote: “Phase 2-3 (expansion to 20 EH/s) – site civils & procurement underway for H2 2024 completion”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ef20020920_ex99-1.htm)
Quote: “Phase 2-3 (expansion to 20 EH/s) – site civils & procurement underway for H2 2024 completion”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”
confirms iren 8-K exhibit (irensepmonthlyupdate4oct.htm)
Quote: “Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”