Remaining 2 Childress Phase 3 buildings complete in December 2024
Company: IREN
What the later record shows
Delivered on time · happened December 31, 2024
By the December 2024 update all six Phase 3 buildings were complete, which includes the two that remained, and Childress operating capacity had reached 350MW.
“6 x 25MW data center buildings now complete, energized and hashing”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Four data center buildings are complete, energized and hashing; the remaining two are in final internal fit-out with progressive completion expected this month.
Source (primary)
iren 8-K exhibit (irenbusinessupdate2dec24.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗
Quote: “2 data center buildings remaining, finalization of internal fit-out and progressive completion expected this month”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenbusinessupdate2dec24.htm)
Quote: “2 data center buildings remaining, finalization of internal fit-out and progressive completion expected this month”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “6 x 25MW data center buildings now complete, energized and hashing”