Childress Phase 6 (100MW) in 2025
Company: IREN
What the later record shows
Outcome not yet confirmed
In February 2025 the 100MW Phase 6 mining expansion was replaced by Horizon 1, a 75MW liquid-cooled AI data center, plus 25MW of mining. Later Childress status charts drop 'Phase 6' entirely, and no passage reports the original 100MW Phase 6 being completed.
“Horizon 1 adjusts prior expansion plan from 57 EH/s to 52 EH/s”
2025-02-11 · iren 8-K exhibit (q2fy25resultspressreleas.htm) View cached copy (2026-10-20)Live source ↗
“Primary Substation 3 Primary Substation 6 Bulk Substation Status Mining (25MW) Horizon 1 (75MW) Utility Substation”
2025-03-05 · iren 8-K exhibit (irenfebmonthlyupdatevf.htm) View cached copy (2026-10-18)Live source ↗
Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 6, adding 100MW, is under construction with expected completion in 2025.
Source (primary)
iren 8-K exhibit (nov2024monthlyupdatevdc.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗
Quote: “Childress Phase 6 (Texas, USA) 100 2025 Under construction”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)
Quote: “Childress Phase 6 (Texas, USA) 100 2025 Under construction”