Childress Phase 1 (100MW) in H1 2024
Company: IREN - Project: Childress
What the later record shows
Delivered on time
On June 5, 2024, total operating capacity was 260MW, which implies the full 100MW of Childress Phase 1 was running. The July update confirms Phase 1 at 100MW, complete and operating.
“260MW operating, 510MW in 2024”
2024-06-05 · iren 8-K exhibit (ef20030723_ex99-1.htm) View cached copy (2026-11-04)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10”
2024-07-04 · iren 8-K exhibit (junemonthlyinvestorupdat.htm) View cached copy (2026-11-01)Live source ↗
Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN targets completion of Childress Phase 1 (first 100MW) in H1 2024, with 60MW operating and 40MW under construction, supporting expansion to 10 EH/s.
Source (primary)
iren 8-K exhibit (ef20025647_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗
Quote: “Phase 1 (first 100MW) – H1 2024 ◾ 60MW operating, 40MW under construction ◾ Supports expansion to 10 EH/s”
How we checked this
Checked on November 10, 2026. The cited source supports every part of this claim.
The update lists Childress Phase 1 (first 100MW) for H1 2024, with 60MW operating, 40MW under construction, and support for expansion to 10 EH/s. It also describes the expansion to 100MW in H1 2024 as nearing completion.
Confirmed in the source:
- Childress Phase 1 covers the first 100MW
- Childress Phase 1 is targeted for H1 2024
- 60MW of Childress Phase 1 was operating
- 40MW of Childress Phase 1 was under construction
- Childress Phase 1 supports expansion to 10 EH/s
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036124016752/ef20025647_ex99-1.htm) in full (14,965 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (ef20025647_ex99-1.htm)
Quote: “Phase 1 (first 100MW) – H1 2024 ◾ 60MW operating, 40MW under construction ◾ Supports expansion to 10 EH/s”
confirms iren 8-K exhibit (junemonthlyinvestorupdat.htm)
Quote: “Childress Phase 1 (Texas, USA) 100 4.8 Complete Operating Total Operating 260 10”
confirms iren 8-K exhibit (ef20030723_ex99-1.htm)
Quote: “260MW operating, 510MW in 2024”