jain.com

Childress Phase 1 remaining 80MW data centers

Company: IREN

Subject kind
facility timeline
Statement date
2023-06-19
Promised by
2024-03-31
Promised amount
80.0 MW
Current status
stated

The claim, verbatim

Construction of the remaining 80MW (4 x 20MW data centers) of Childress Phase 1, at the 600MW Childress site, is underway and targeted for completion by early 2024 (indicative timing).

Source (primary)

iren 8-K exhibit (brhc20054635_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-23)Live source ↗

Quote: “The additional 4 x 20MW data centers are expected to increase the Company's potential operating capacity by ~63% (from 5.6 EH/s to 9.1 EH/s 1 ) and is targeted for completion by early 2024”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (brhc20054635_ex99-1.htm)

Quote: “The additional 4 x 20MW data centers are expected to increase the Company's potential operating capacity by ~63% (from 5.6 EH/s to 9.1 EH/s 1 ) and is targeted for completion by early 2024”

View cached copy (2026-11-23)Live source ↗