Childress data center expansion to 650MW
Company: IREN - Project: Childress
What the later record shows
Delivered on time · happened June 30, 2025
The 10-K states that as of June 30, 2025 Childress had approximately 650MW of operating data center capacity, which meets the 650MW target.
“as of June 30, 2025, has approximately 650MW of operating data center capacity and installed hashrate capacity of approximately 40.1 EH/s”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗
Checked October 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN is expanding data center capacity at Childress, targeting 650MW to support its hashrate expansion to 50 EH/s in the first half of 2025.
Source (primary)
iren 8-K exhibit (irenlimited-exx994mar2025.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-15)Live source ↗
Quote: “We are currently undertaking an expansion of our data center capacity at Childress, targeting 650MW to support our hashrate expansion to 50 EH/s in the first half of 2025”
How we checked this
Checked on October 17, 2026. The cited source supports every part of this claim.
The filing states that IREN is expanding Childress data center capacity, targeting 650MW, to support its hashrate expansion to 50 EH/s in the first half of 2025.
Confirmed in the source:
- IREN is expanding data center capacity at its Childress site
- The Childress expansion targets 650MW
- The expansion supports IREN's hashrate expansion to 50 EH/s
- The 50 EH/s target is for the first half of 2025
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000187884825000043/irenlimited-exx994mar2025.htm) in full (129,213 characters, retrieved October 15, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (irenlimited-exx994mar2025.htm)
Quote: “We are currently undertaking an expansion of our data center capacity at Childress, targeting 650MW to support our hashrate expansion to 50 EH/s in the first half of 2025”
confirms IREN 10-K filed 2025-08-28
Quote: “as of June 30, 2025, has approximately 650MW of operating data center capacity and installed hashrate capacity of approximately 40.1 EH/s”