Childress 300MW under construction for H1 2025
Company: IREN
What the later record shows
Delivered; the record does not say when
By July 2, 2025 IREN reported 810MW of operating data centers, the promised total, and Childress later shows about 650MW operating (350MW plus 300MW). No passage says whether this was reached by June 30, 2025.
“Next-Generation Data Centers : 810MW of operating data centers underpinning three verticals: Bitcoin Mining, AI Cloud Services and AI Data Centers.”
2025-07-02 · iren 8-K exhibit (ef20051566_ex99-1.htm) View cached copy (2026-10-11)Live source ↗
“Our 750MW Childress site has been operating since April 2023 and, as of September 30, 2025, has approximately 650MW of operating data center capacity”
2025-11-05 · IREN 10-Q filed 2025-11-06 View cached copy (2026-08-31)Live source ↗
Checked October 18, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
At Childress, 300MW of capacity is under construction for H1 2025, taking total data center capacity to 810MW.
Source (primary)
iren 8-K exhibit (irenfebmonthlyupdatevf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-18)Live source ↗
Quote: “Under Construction H1 2025 (300MW)”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenfebmonthlyupdatevf.htm)
Quote: “Under Construction H1 2025 (300MW)”
confirms IREN 10-Q filed 2025-11-06
Quote: “Our 750MW Childress site has been operating since April 2023 and, as of September 30, 2025, has approximately 650MW of operating data center capacity”
confirms iren 8-K exhibit (ef20051566_ex99-1.htm)
Quote: “Next-Generation Data Centers : 810MW of operating data centers underpinning three verticals: Bitcoin Mining, AI Cloud Services and AI Data Centers.”