Childress Phase 5 energization

Company: IREN

Subject kind
facility timeline
Statement date
2025-04-03
Promised by
2025-06-30
Promised amount
150.0 MW
Current status
verified

What the later record shows

Delivered on time

Childress had 500MW operating (Phases 1-4) in early May 2025, and Phase 5 energization was still 'in coming weeks' on June 4. By June 29, 2025 the site supported 650MW of operating capacity, implying the 150MW Phase 5 came online before June 30, though no passage names an exact energization date.

“Phase 1-4 (500MW) now fully operational • Phase 5 (150MW) structures nearing completion”
2025-05-05 · iren 8-K exhibit (aprilmonthlyupdatevf.htm) View cached copy (2026-10-16)Live source ↗
“Phase 5 (150MW) energization in coming weeks, with substation transformer now installed”
2025-06-04 · iren 8-K exhibit (ex991may2025monthlyupdat.htm) View cached copy (2026-10-13)Live source ↗
“50 EH/s Milestone Achieved The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗

Checked October 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Childress Phase 5 (150MW) is on track for energization in the coming months, shown as H1 2025.

Source (primary)

iren 8-K exhibit (pressreleasemarch2025mon.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-17)Live source ↗

Quote: “Phase 5 (150MW) new data centers on track for energization in coming months”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (pressreleasemarch2025mon.htm)

Quote: “Phase 5 (150MW) new data centers on track for energization in coming months”

View cached copy (2026-10-17)Live source ↗

confirms iren 8-K exhibit (a50ehsupdate_vff.htm)

Quote: “50 EH/s Milestone Achieved The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”

View cached copy (2026-10-11)Live source ↗

confirms iren 8-K exhibit (ex991may2025monthlyupdat.htm)

Quote: “Phase 5 (150MW) energization in coming weeks, with substation transformer now installed”

View cached copy (2026-10-13)Live source ↗

confirms iren 8-K exhibit (aprilmonthlyupdatevf.htm)

Quote: “Phase 1-4 (500MW) now fully operational • Phase 5 (150MW) structures nearing completion”

View cached copy (2026-10-16)Live source ↗

Record of changes

October 17, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 17, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.