Childress expansion to 350MW in 2024

Company: IREN

Subject kind
facility capacity
Statement date
2024-05-14
Promised by
2024-12-31
Promised amount
350.0 MW
Current status
verified

What the later record shows

Delivered on time · happened December 31, 2024

IREN reported 350MW of data center capacity at Childress as of December 31, 2024, meeting the 2024 target. Phase 3 was also reported complete and energized in the December 2024 update.

“6 x 25MW data center buildings now complete, energized and hashing”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
“It has been operating since April 2023 and, as of December 31, 2024, has 350MW of data center capacity and hashrate capacity of approximately 21.1 EH/s.”
2025-03-19 · iren 8-K exhibit (irenlimited-exx992dec2024x.htm) View cached copy (2026-10-18)Live source ↗

Checked November 5, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN is targeting expansion of data center capacity at its Childress, Texas site to 350MW in 2024 and has commenced construction of Phase 2 (additional 100MW) and Phase 3 (additional 150MW).

Source (primary)

iren 8-K exhibit (ef20027345_ex99-4.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-05)Live source ↗

Quote: “We are targeting expansion of our data center capacity at Childress to 350MW in 2024 and have commenced construction for Childress Phase 2 (additional 100MW) and Phase 3 (additional 150MW).”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (ef20027345_ex99-4.htm)

Quote: “We are targeting expansion of our data center capacity at Childress to 350MW in 2024 and have commenced construction for Childress Phase 2 (additional 100MW) and Phase 3 (additional 150MW).”

View cached copy (2026-11-05)Live source ↗

confirms iren 8-K exhibit (irenlimited-exx992dec2024x.htm)

Quote: “It has been operating since April 2023 and, as of December 31, 2024, has 350MW of data center capacity and hashrate capacity of approximately 21.1 EH/s.”

View cached copy (2026-10-18)Live source ↗

confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)

Quote: “6 x 25MW data center buildings now complete, energized and hashing”

View cached copy (2026-10-21)Live source ↗

Record of changes

November 5, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 5, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.