jain.com

80MW Childress data center expansion

Company: IREN - Project: Childress

Subject kind
facility timeline
Statement date
2023-11-29
Promised by
2024-06-30
Promised amount
80.0 MW
Current status
verified

What the later record shows

Delivered on time · happened June 30, 2024

This is the same 80MW expansion as claim 6410. By June 30, 2024, Childress Phase 1 at 100 MW was operating and total operating hashrate reached the targeted 10 EH/s, which is consistent with on-time delivery.

“as of June 30, 2024, has approximately 100 MW of data center capacity and hashrate capacity of approximately 4.8 EH/s”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Operating Total Operating 260 10.0”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

80MW data center expansion at Childress on track to be progressively delivered from January 2024 through Q2 2024

Source (primary)

IREN 6-K filed 2023-11-30 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The Company's 80MW data center expansion at Childress remains on track to be progressively delivered from January 2024 through to Q2 2024”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The filing states that the 80MW Childress expansion remains on track for progressive delivery from January 2024 through Q2 2024.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1878848/000114036123055324/ef20015516_6k.htm) in full (13,414 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms IREN 6-K filed 2023-11-30

Quote: “The Company's 80MW data center expansion at Childress remains on track to be progressively delivered from January 2024 through to Q2 2024”

View cached copy (2026-08-31)Live source ↗

confirms IREN 20-F filed 2024-08-28

Quote: “as of June 30, 2024, has approximately 100 MW of data center capacity and hashrate capacity of approximately 4.8 EH/s”

View cached copy (2026-08-31)Live source ↗

Record of changes

September 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 4, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.