Childress Commercial Operations deadline
Company: IREN
What the later record shows
Delivered on time · happened March 31, 2025
Childress has been operating since April 2023 and had 500 MW of capacity by March 31, 2025, before the December 31, 2025 Commercial Operations deadline. The passages do not use the agreement's formal term 'Commercial Operations'.
“Our 750MW site in Childress has been operating since April 2023 and, as of March 31, 2025, had 500MW of data center capacity”
2025-05-13 · iren 8-K exhibit (irenlimited-exx994mar2025.htm) View cached copy (2026-10-15)Live source ↗
Checked October 17, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Owner agreed that the Childress project will achieve Commercial Operations on or before December 31, 2025.
Source (primary)
Childress County TX tax abatement - US IE Hardware- Phase 3 (CHILDRESS_CO_TX, records_response)
View cached copy (2026-10-17)Live source ↗
Quote: “Owner agrees that the Project shall achieve Commercial Operations on or before December 31, 2025.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Childress County TX tax abatement - US IE Hardware- Phase 3
Quote: “Owner agrees that the Project shall achieve Commercial Operations on or before December 31, 2025.”
confirms iren 8-K exhibit (irenlimited-exx994mar2025.htm)
Quote: “Our 750MW site in Childress has been operating since April 2023 and, as of March 31, 2025, had 500MW of data center capacity”