Childress Phases 2-3 (200MW) in H2 2024
Company: IREN - Project: Childress
What the later record shows
Delivered on time · happened December 31, 2024
Phases 2-3 were upsized to 250MW. By the end of December 2024, Childress showed 350MW complete and operating, which is Phase 1's 100MW plus Phases 2-3's 250MW, within H2 2024.
“Phase 3 Substation (150MW) energized • 4 data center buildings complete, energized and hashing”
2024-12-05 · iren 8-K exhibit (nov2024monthlyupdatevdc.htm) View cached copy (2026-10-24)Live source ↗
“Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
Checked November 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phases 2 and 3, adding 200MW to support expansion to 20 EH/s, are under construction with H2 2024 timing.
Source (primary)
iren 8-K exhibit (ef20023430_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-09)Live source ↗
Quote: “Childress Phase 2-3 (Texas USA) 200 10.0 7 H2 2024 Under construction”
How we checked this
Checked on November 11, 2026. The cited source supports every part of this claim.
The construction update and capacity table state the 200MW size, the link to the 20 EH/s expansion, the under-construction status and the H2 2024 timing.
Confirmed in the source:
- Childress Phases 2 and 3 comprise the next 200MW at the site.
- Childress Phases 2 and 3 support expansion to 20 EH/s.
- Childress Phases 2-3 are listed as under construction.
- Childress Phases 2-3 are listed with H2 2024 timing.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036124011575/ef20023430_ex99-1.htm) in full (16,339 characters, retrieved November 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (ef20023430_ex99-1.htm)
Quote: “Childress Phase 2-3 (Texas USA) 200 10.0 7 H2 2024 Under construction”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “Childress (Texas, USA) 350 21.1 Complete Operating Total Operating 510 31”
confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)
Quote: “Phase 3 Substation (150MW) energized • 4 data center buildings complete, energized and hashing”