Childress Phase 2 substation construction start
Company: IREN - Project: Childress
What the later record shows
Delivered; the record does not say when
The August 2024 update says the Childress Phase 2 100MW substation was energized, so construction plainly took place. No passage says when construction began, so a March 2024 start cannot be confirmed.
“Childress Phase 2 (100MW) – 3Q 2024 o 100MW substation energized o 4 x 25MW data centers on track for completion by the end of next month”
2024-08-05 · iren 8-K exhibit (irenjuly2024monthlyupdat.htm) View cached copy (2026-10-31)Live source ↗
Checked November 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Construction of the Childress Phase 2 substation is to commence in March 2024.
Source (primary)
iren 8-K exhibit (ef20023430_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-09)Live source ↗
Quote: “Phase 2 substation construction to commence this month”
How we checked this
Checked on November 11, 2026. The cited source supports every part of this claim.
The update is dated March 6, 2024 and says Phase 2 substation construction will commence this month, which means March 2024.
Confirmed in the source:
- Construction of the Childress Phase 2 substation was to commence in March 2024, as the update dated March 6, 2024 says it would start "this month".
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036124011575/ef20023430_ex99-1.htm) in full (16,339 characters, retrieved November 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms iren 8-K exhibit (ef20023430_ex99-1.htm)
Quote: “Phase 2 substation construction to commence this month”
confirms iren 8-K exhibit (irenjuly2024monthlyupdat.htm)
Quote: “Childress Phase 2 (100MW) – 3Q 2024 o 100MW substation energized o 4 x 25MW data centers on track for completion by the end of next month”