Childress data center expansion to 650MW
Company: IREN
What the later record shows
Delivered on time · happened June 29, 2025
The June 29, 2025 release says Childress was supporting 650MW of operating capacity. The 10-K lists Childress at 650MW operating as of June 30, 2025.
“The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗
“Childress BTC Mining (Texas, USA) 650 40.1 Operating Total Operating 810 50.0”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗
Checked October 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN is expanding Childress data center capacity, targeting 650MW in the first half of 2025 to support growth to 50 EH/s of hashrate.
Source (primary)
iren 8-K exhibit (irenlimited-exx994dec2024.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-20)Live source ↗
Quote: “targeting 650MW to support expansion to 50 EH/s of our hashrate in the first half of 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenlimited-exx994dec2024.htm)
Quote: “targeting 650MW to support expansion to 50 EH/s of our hashrate in the first half of 2025”
confirms IREN 10-K filed 2025-08-28
Quote: “Childress BTC Mining (Texas, USA) 650 40.1 Operating Total Operating 810 50.0”
confirms iren 8-K exhibit (a50ehsupdate_vff.htm)
Quote: “The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”