Childress Phase 4 & 5 add 300MW

Company: IREN

Subject kind
facility capacity
Statement date
2024-12-01
Promised by
2025-06-30
Promised amount
300.0 MW
Current status
verified

What the later record shows

Delivered on time · happened June 29, 2025

Childress grew from 350MW to 650MW of operating capacity by June 29, 2025. That is the +300MW from Phases 4 and 5, delivered within H1 2025.

“Phase 4 (150MW) energized, with site operating data centers increased to 500MW”
2025-04-03 · iren 8-K exhibit (pressreleasemarch2025mon.htm) View cached copy (2026-10-17)Live source ↗
“The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗

Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The H1 2025 expansion will come from Childress Phases 4 and 5, adding 300MW, with earthworks and foundation works ongoing.

Source (primary)

iren 8-K exhibit (irenbusinessupdate2dec24.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗

Quote: “Single site expansion at Childress, through Childress Phase 4 & 5 (+300MW) with earthworks and foundation works ongoing”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (irenbusinessupdate2dec24.htm)

Quote: “Single site expansion at Childress, through Childress Phase 4 & 5 (+300MW) with earthworks and foundation works ongoing”

View cached copy (2026-10-24)Live source ↗

confirms iren 8-K exhibit (a50ehsupdate_vff.htm)

Quote: “The 50 EH/s milestone is anchored by our 750MW Childress site, now supporting 650MW of operating capacity”

View cached copy (2026-10-11)Live source ↗

confirms iren 8-K exhibit (pressreleasemarch2025mon.htm)

Quote: “Phase 4 (150MW) energized, with site operating data centers increased to 500MW”

View cached copy (2026-10-17)Live source ↗

Record of changes

October 24, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 24, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.