Childress Phase 2 (100MW) in 3Q CY24
Company: IREN
What the later record shows
Delivered on time · happened September 30, 2024
In August, Childress showed 140MW operating with Phase 2 still under construction. The September update shows Childress at 200MW complete and operating, and Phase 2 is no longer listed as under construction, which implies Phase 2 finished by the end of September.
“Childress (Texas, USA) 140 7.3 Complete Operating Total Operating 300 16”
2024-09-04 · iren 8-K exhibit (irenaug2024monthlyupdate.htm) View cached copy (2026-10-29)Live source ↗
“Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”
2024-10-03 · iren 8-K exhibit (irensepmonthlyupdate4oct.htm) View cached copy (2026-10-26)Live source ↗
Checked October 30, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Childress Phase 2, a 100MW expansion, is scheduled for 3Q CY24; the 100MW substation is energized and 40MW of data centers are commissioned.
Source (primary)
iren 8-K exhibit (fy24resultspressreleasev.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-30)Live source ↗
Quote: “Childress Phase 2 (100MW, 3Q CY24) – 100MW substation energized, 40MW data centers commissioned”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (fy24resultspressreleasev.htm)
Quote: “Childress Phase 2 (100MW, 3Q CY24) – 100MW substation energized, 40MW data centers commissioned”
confirms iren 8-K exhibit (irensepmonthlyupdate4oct.htm)
Quote: “Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”
confirms iren 8-K exhibit (irenaug2024monthlyupdate.htm)
Quote: “Childress (Texas, USA) 140 7.3 Complete Operating Total Operating 300 16”