Childress Phase 1 remaining 60MW in H1 2024
Company: IREN
What the later record shows
Delivered on time · happened June 30, 2024
In May 2024, 85MW of Childress Phase 1 was operating and 15MW was under construction. The 20-F property table as of June 30, 2024 lists the full 100MW of Phase 1 as operating, which is within H1 2024.
“The following table reflects our current properties as of June 30, 2024, that are either operational, under construction or in development”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗
“Childress Phase 1 (Texas, USA) 100 4.8 Operating Total Operating 260 10.0”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗
Checked November 12, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The remaining 60MW (3.8 EH/s) of Childress Phase 1 is under construction, with indicative delivery commencing in H1 2024.
Source (primary)
iren 8-K exhibit (ef20020920_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-12)Live source ↗
Quote: “Childress Phase 1 (Texas, USA) 60 3.8 8 H1 2024 9 Under construction”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ef20020920_ex99-1.htm)
Quote: “Childress Phase 1 (Texas, USA) 60 3.8 8 H1 2024 9 Under construction”
confirms IREN 20-F filed 2024-08-28
Quote: “The following table reflects our current properties as of June 30, 2024, that are either operational, under construction or in development”